Deliverable five year housing land supply statement 1 April 202 4to 31 March 2029

How to search the page

iOS Safari – tap the action icon (square with arrow at bottom of screen) and select ‘find on page’ from the list of options.
Other mobile browsers – tap the browser’s options menu (usually 3 dots or lines) and select ‘find on page’ from the options.
CTRL + F on your keyboard (Command + F on a Mac)
This will open a search box on the page. Type the word you are looking for in the search box and press enter. The word will then be highlighted wherever it appears in the guidance. Use the navigation in the search box to move to the next word found.

How to print a copy of the page

iOS Safari – tap the action icon (square with arrow at bottom of screen) and select ‘print’ from the list of options.
Other mobile browsers – tap the browser’s options menu (usually 3 dots or lines) and select ‘print’ or select ‘share’ from the list of options, then ‘print’ in the popup.
CTRL + P on your keyboard (Command + P on a Mac)
You have an option to print the entire page, or select a page range.

1.0 Introduction

1.1 The National Planning Policy Framework 2023(NPPF), sets out the government’s planning policies for delivering a sufficient supply of homes. Paragraph 76states that local planning authorities are not required to identify and update annually a supply of specific deliverable sites sufficient to provide a minimum of five years’ worth of housing for decision making purposes if the following criteria are met: 

  • a) their adopted plan is less than five years old
  • b0 and b) that adopted plan identified at least a five year supply of specific, deliverable sites at the time that its examination concluded. 

1.2 Paragraph 77 goes on to state that in all other circumstances, local planning authorities should identify and update annually a supply of specific deliverable sites sufficient to provide either a minimum of five years’ worth of housing, or a minimum of four years’ worth of housing if the provisions in paragraph 226 apply. The supply should be demonstrated against either the housing requirement set out in adopted strategic policies, or against the local housing need where the strategic policies are more than five years old. Where there has been significant under delivery of housing over the previous three years, the supply of specific deliverable sites should in addition include a buffer of 20% (moved forward from later in the plan period).

1.3 In Blackpool’s case, this statement sets out Blackpool’s deliverable five year housing land supply for the period 1 April 2024 to 31 March 2029 against the local housing need (standard method figure) as Blackpool’s strategic housing policy is more than five years old.

2.0 The five year housing requirement

2.1The Blackpool Local Plan Part 1: Core Strategy (Core Strategy) was adopted in January 2016 and sets out the housing requirement for Blackpool. Core Strategy Policy CS2 (Housing Provision) states that provision will be made for the delivery of 4,200 new homes in Blackpool between 2012 and 2027. Paragraph 5.20 of the supporting text sets out that this is a phased target equating to: 

  • 250 dwellings per annum between 2012 to 2017 
  • 280 dwellings per annum between 2017 to 2022 
  • 310 dwellings per annum between 2022 to 2027 

This is an average of 280 dwellings per annum.

2.2 However, as the core strategy was adopted over five years ago (January 2016), paragraph 77 of NPPF is relevant. It states ‘supply should be demonstrated against either the housing requirement set out in adopted strategic policies, or against the local housing need (standard method) where the strategic policies are more than five years old’.

2.3 Blackpool’s local housing need calculated using the standard method (2024)with respect to the five year supply for the five year period 1 April 2024 to 31 March 2029 is 735 dwellings (147 per annum).

2.4 PPG states that the 5% buffer should be increased to 20% where there has been significant under delivery of housing over the previous 3 years, to improve the prospect of achieving the planned supply. PPG further explains that this is where delivery of housing taken as a whole over the previous 3 years, has fallen below 85% of the requirement, as set out in the last published housing delivery test results.

2.5 The 2023 housing delivery test results have not yet been made available. As a result, the 2022 housing delivery test results have been used in this paper to determine the buffer required when calculating the 5 year supply requirement.

2.6 The 2022 housing delivery test results indicate that Blackpool has significantly over-delivered against the number of homes required (see Table 1) so a 5% buffer is relevant.

Table 1: 2022 housing delivery test results

Details of homes delivered
Number of homes required
2019 to 20
Number of homes required 2020 to 21Number of homes required
2021 to 22
Total number of homes requiredHomes delivered
2019 to 20
Homes delivered
2020 to 21
Homes delivered
2021-22
Total number of homes deliveredHousing delivery test: 2020 measurement

104

81

130

315

335

161

267

763

242%

2.7 Therefore, for the purposes of the five year supply calculation for the period 2024 to 2029,the five year requirement incorporating a 5% buffer is calculated to be 772 dwellings, which is 154 dwellings per annum (Table 2).

Table2: Blackpool Five year supply housing requirement breakdown

supply breakdown
ReferenceDescriptionNumber

A

Local housing need calculated using the standard method 2024 – 2029 

735

B

5% buffer (5% of 735)

37

C

Five year requirement incorporating buffer (A + B)

772

D

Annual requirement for next five years (C/5)

154

3.0 The deliverable supply

3.1 The NPPF states that to be considered deliverable, sites for housing should be available now, offer a suitable location for development now, and be achievable with a realistic prospect that housing will be delivered on the site within five years. 

3.2 The NPPF advises that sites which do not involve major development and have outline planning permission, and all sites with detailed planning permission, should be considered deliverable until permission expires, unless there is clear evidence that homes will not be delivered within five years. These deliverable sites are set out in table A of appendix 1.

3.3 Correspondence has been undertaken with developers on the largest sites with detailed planning permission in relation to build out rates and realistic delivery over the five year period.

3.4 In total, a deliverable supply of 659 new build dwellings on sites with detailed planning permission, or which do not involve major development and have outline planning permission, are identified in table A of appendix 1. For the purposes of this assessment, sites with reserved matters approval are considered to have detailed permission, because the permissions can now be implemented and in some cases the sites are under construction.

3.5 In addition there are 92 dwellings that have detailed planning permission in the form of conversions and changes of use as part of major schemes (10 dwellings or more), which are identified in table B of appendix 1. There are also 67 dwellings that have detailed planning permission in the form of conversions and changes of use as part of minor schemes (9 or fewer dwellings), which are identified in table C of appendix 1.

3.6 The NPPF advises that where a site has outline permission for major development, has been allocated in a development plan, has a grant of permission in principle, or is identified on a brownfield register, it should only be considered deliverable where there is clear evidence that housing completions will begin on site within five years. 

3.8T he housing site allocations in the Blackpool Local Plan Part 2: Site Allocations and Development Management Policies are considered to be deliverable over the five year period. These sites equate to 367 dwellings and are listed in table D of appendix 1.

3.9 The NPPF allows local planning authorities to make an allowance for windfall sites as part of their anticipated supply, if there is compelling evidence that they will provide a reliable source of supply. The issue of windfall housing provision was considered by the Blackpool core strategy inspector (paragraph 42 of the inspector’s report). He notes that the majority of windfall site developments in Blackpool are anticipated to be conversions (notably of hotels and guest houses) in the inner areas and that the council is encouraging such schemes in appropriate circumstances as part of its regeneration strategy. He considered that there was compelling evidence that windfalls will continue to provide a reliable source of housing land supply during the plan period. This is reflected in core strategy policy CS2, which identifies windfall housing as one of the three sources of housing provision in Blackpool.

3.10 Looking specifically at conversions, table 3 below provides up to date information about this type of windfall development. It shows that from 2012-2024, 1,427 dwellings were completed on windfall sites through conversions/changes of use 

Table 3: Windfall housing completions

Conversions/changes of use: Permitted and CLDE/CLUP/CPA

Detail of windfall housing completions
YearSmall sitesMajor sitesTotal

2012/13

99

24

123

2013/14

129

22

151

2014/15

148

31

179

2015/16

149

12

161

2016/17

95

16

111

2017/18

117

10

127

2018/19

115

14

129

2019/20

153

31

184

2020/21 *

50

11

61

2021/22

39

40

79

2022/23

71

39

110

2023/24

12

0

12

Total

1177

250

1427

*It should be noted that these figures have been affected by the Covid-19 pandemic

3.11 Table 3 shows that the most consistent source of windfall completions has been conversions/changes of use on small sites (sites of 9 dwellings or less). This includes dwellings provided through permitted conversions, prior approvals for change of use and lawful development certificates. An average of 98 dwellings per year have been provided through these sources. 

3.12 This source of supply is expected to continue because core strategy policy CS23 allows more hotels and guest houses to change to residential uses than previous policy approaches. In addition, in 2015 the council established Blackpool Housing Company, which acquires poor quality existing homes and redundant buildings, such as former holiday accommodation and remodels them into quality affordable homes for rent. They have a development programme which aims to deliver between 80 and 100 quality homes per year. Although not all of these homes will be net additions to the stock, this work will further boost the supply of dwellings created through conversions and changes of use.

3.13 Conversions/changes of use on larger sites (sites of over 9 dwellings) also come forward (at an average of 21 per year since 2012), but the figures can be unduly influenced by larger schemes which come forward on an irregular basis (such as the scheme for 66 apartments that is currently under construction at 647-651 New South Promenade). New build windfall sites also tend to come forward, but not on a consistent basis.

3.14 Therefore, taking account of completion evidence it is considered appropriate to use a windfall allowance of 98 dwellings per year based upon conversions/changes of use on small sites of 9 units or less, which have consistently delivered housing over the plan period. Any new build windfall sites or major conversions/changes of use that come forward will be in addition to the windfall allowance.

3.15 At 31 March 2024 there were 67 dwellings permitted in conversions/change of use schemes on small sites. To avoid double counting, these permitted dwellings are incorporated into the windfall allowance. Table 4 sets out the deliverable housing supply.

Table 4: Deliverable housing supply

Details of supply
Source of SupplyNumber of dwellings

New build sites that do not involve major development and have outline planning permission and sites with detailed planning permission

659

Major conversions and changes of use with detailed planning permission

92

Minor conversions and changes of use with detailed planning permission

67

Windfall allowance for minor conversions and changes of use (490 minus 67 dwellings with permission)

423

Other deliverable sites

367

Total

1608

3.16 The five year target incorporating a 5% buffer is calculated to be 772 dwellings. A supply of 1608 dwellings has been identified. This equates to around a 10.44 year deliverable housing supply. Therefore, the council can currently demonstrate a five year deliverable housing supply, in accordance with the requirements of the NPPF. 

Appendix 1: Deliverable housing sites

Table A: New build sites with detailed permission at 1 April 2024

Details of housing sites
Application numberAddressTotal capacity (net)Dwellings left to be built (at 1 April2024)Deliverable dwellings over 5 year periodComments

17/0095

Land at Moss House Road

422

296

120 

Dwellings under construction

18/0590 

Site of Former Kings Christian Centre

15

15

15

Dwellings under construction 

20/0189

All Hallows Rectory, 86 All Hallows Road

2

2

2

Non-major site with outline permission.

20/0677

Land at 2C Ball Street

5

1

1

Site under construction

21/0215

Land adjacent to 8 Cottesmore Place, FY3 8SB

1

1

1

Non-major site with outline permission.

20/0495

Land Adjacent to 71 Moss House Road, FY4 5JF

4

4

4

Non-major site with outline permission.

21/0213

16 Kentmere Drive, FY4 4TN

1

1

1

Site with detailed permission.

20/0091

170 Preston New Road, 15 & 17 Carson Road, FY4 4HE

6

6

6

Site with detailed permission.

21/0503

Land adjacent to 14 Strathdale

1

1

1

Site with detailed permission.

21/0124

Land to the rear of 91A North Park Drive, FY3 8NH

1

1

1

Site with detailed permission.

21/0486

Land bound by Chepstow Road/Gateside Drive and Land to the West of Dinmore Avenue 

131

53

53

Dwellings under construction 

21/0537 

Land at the rear of 17 and 21 Moss House Road, FY4 5JF

5

5

5

Site with detailed permission.

21/0804

Land adjacent to 71 Moss House Road, FY4 5JF

14

14

14

Site with detailed permission 

20/0250

Barn adjacent to 36 Moss House Road, FY4 5JE

1

1

1

Site with detailed permission

21/0102

All Hallows Rectory, 86 All Hallows Road, 

1

1

1

Site with detailed permission

21/0264

57 Boothley Road, FY1 3RS

4

4

4

Non-major site with outline permission.

21/1053

12 Broadway, FY4 2JX

2

2

2

Site with detailed permission

21/0678

29 Boome Street, FY4 2JX

3

3

3

Site with detailed permission

22/0299

306 Queens Promenade, FY2 9AD

1

1

1

Site with detailed permission

21/1062

Land at 8 Norbreck Road, FY5 1RP

35

35

35

Site with detailed permission

21/0904

Land to the rear of former Hawes Side Library, Hawes Side Lane

8

8

8

Site with detailed permission

19/0679 

Land to the rear of Ma Kelly’s. 44-46 Queen’s Promenade, FY2 9RW

20

20

20

Site with detailed permission

22/0422

45-47 Bond Street, FY4 1BW

2

2

2

Site with detailed permission

22/0440

Princess Street, Blundell Street, Rigby Road & Tyldesley Road

88

88

88

Dwellings under construction.

22/0254 

24 Low Moor Road, FY2 0PG

5

5

5

Site with detailed permission

22/0499

6 Whinney Heys Road, FY3 8NP

1

1

1

Site with detailed permission

20/0794

Land at Ryscar Way

51

51

51

Site under construction

23/0248

Land at 58 Common Edge Road, FY4 5AU

4

4

4

Site with detailed permission

21/1078

6-8 Carlin Gate, FY2 9QX

3

3

3

Site with detailed permission

23/0359

Land at Bridge House Road

4

4

4

Site with detailed permission

24/0004

67 Chepstow Road (Former GP Housing Office

2

2

2

Site with detailed permission

22/0670

Former Bispham High School, Bispham Road

200

200

200

Site under construction

 N/A

Total

 N/A  N/A

659

 N/A